DEPDev ‘very concerned’ over flagship project delays

DELAYS in implementing infrastructure flagship projects (IFPs) could drive up costs and diminish their economic benefits, the Department of Economy, Planning, and Development (DEPDev) warned.
DEPDev Secretary Arsenio M. Balisacan expressed concern that most IFPs targeted for completion by 2028 are currently behind schedule.
Data from DEPDev showed that 33 of the 37 IFPs targeted for completion from 2026 to 2028 were behind schedule as of September, while only four were on schedule. The 37 projects have a combined indicative cost of P1.45 trillion.
“We are very concerned. That is why we are focusing on the monitoring of those projects and especially the availability of funding,” he told reporters on the sidelines of the 64th Philippine Economic Society Annual Meeting and Conference on Nov. 20.
All six projects targeted for completion this year are behind schedule, along with nine of the 12 projects due in 2027, and 18 of the 19 projects due in 2028.
Mr. Balisacan said delays would mean foregoing the benefits the projects could have delivered.
“Number one, you forego the benefits that they would have brought,” he said. “If you delay that, the benefits will be reduced. Because the benefits are far into the future, if you discount to the present, it’s already low.”
“Number two, it becomes more costly to complete the project because the project proponents or implementers would come back to us to ask for adjustment in the cost because of the impact of changes in prices,” he added.
Mr. Balisacan noted major projects, such as railways and highways, become much more expensive to complete if they are delayed.
Among the projects targeted for completion in 2028 but running behind schedule were the P735.63-billion New Manila International Airport, the P77-billion Metro Rail Transit Line 7 Project, the P70.81-billion Davao City Bypass Construction Project and the P28.78-billion Cebu Bus Rapid Transit Project.
Of the 37 projects targeted for completion by 2028, seven reported issues involving site conditions or availability, including right-of-way concerns. Three faced procurement issues and two had budget and funds flow concerns.
The number of IFPs targeted for completion by 2028 fell to 37 in the third quarter of 2026 from 60 in the second quarter of 2025, reflecting completed projects, revised schedules and changes in the project list, DEPDev data showed.
It noted that 19 projects had been rescheduled for completion beyond 2028.
As of September, the government’s IFP portfolio comprised of 201 projects with an indicative total cost of P10.25 trillion.
Eight had been completed from 2023 to 2025, while 156 were targeted for completion beyond 2028.
Across the full IFP portfolio, site issues were the most commonly reported implementation concerns, affecting 21 projects. Procurement issues affected 12 projects, while eight projects reported design, scope or technical issues and another eight reported budget and funds flow concerns.
DEPDev identified aligning budget programming with project completion schedules as a key action, with priority given to projects at advanced stages of readiness and with confirmed delivery timelines.
It also called for updated completion action plans for delayed projects, with clear milestones and accountability, and stronger coordination to resolve right-of-way and permitting constraints.
Under the proposed 2027 national budget, P44.5 billion is allocated to 18 IFPs targeted for completion by 2028, according to DEPDev. — Justine Irish D. Tabile

Related posts

Philippine peso falls to new all-time low P62.565 vs dollar

Michael H. Henry

Before the explosive drives, Derrick Rose found peace in Bob Marley

Michael H. Henry

1Life, Singapore Diagnostics expand free lab testing for PhilHealth members

Michael H. Henry